How to run a Progress Payment Report

This article will walk you through the components of running a Progress Payment Report for your Pay Estimate.

NOTE: Due to the configurable nature of the FACS Platform, the specific name of some Labels or Field Names may differ from this example and your portal.

The Progress Payment Report can be generated by first accessing your project, followed by opening the project Reports Page:

Report images for Support Site (3)

 

# Description
1 Select your project
2 Click the Reports button
3 Once the report Page has opened, select Progress Payment

 

 

FACS_Report images for Support Site_Prog Pay Selection Criteria

# Description
1 Select the Pay Estimate
2 Click Compile Report

NOTE: If you are running a "Progress Payment by Fiscal Share" Report, you will also have a Fiscal Shares Selection option

Once the report compiles, you can view the report within FACS:

 

# Description Details
1 Pay Estimate Period Displays the Pay Estimate of this report from Data --> Payment Settings --> Pay Estimate
2 Portal Name Name of the Client Portal
3 Project Name Project Name
4 Project Number Displays the Project Number from  Project Information
5 Report Name Name of the Report
6 Construction Start Date Displays the Construction Start Date from  Project Information
7 Estimated Completion Date Displays the Estimated Completion Date from  Project Information
8 Item Number Displays the Item No
9 Sequence Number Displays the Seq. Number
10 Item Description Displays the Description of the Item
11 UOM Unit of Measure
12 Unit Price Unit Price of the Item
13 Authorized Quantity Current Authorized Quantity of the Item
14 Period Quantity Recorded SUM of the Quantity entered in Approved status Inspector Daily Reports --> Item Detail with an IDR Report Date within the Pay Period Date Range
15 Period Stockpile SUM of the Quantity entered in Stockpile Service for the item within the Pay Period Date Range
16 Period Quantity SUM of the Quantity entered in Approved status Inspector Daily Reports --> Item Detail with an IDR Report Date within the Pay Period Date Range & permitted for payment because there are no restrictions such as Item Overrun or Material Acceptance not fulfilled
17 Period Payment Calculation of "Period Quantity" * Unit Price
18 Material Acceptance to Date SUM of Material Acceptance entered in the Material Acceptance Service for the item up to the end date of the payment period
19 Quantity to Date SUM of all "Period Qty" up to and including the current pay period
20 Stockpile to Date SUM of Stockpile entered in the Stockpile Service for the item up to the end date of the payment period
21 Payment to Date Calculation of "Quantity to Date" * Unit Price"
22 Hold Payment Flag A 'flag' will appear if the Item "Requires MA" (based on checkbox associated with the item) and does not have enough Material Acceptance entered for the full qty to be paid, or if there is not enough Authorized Quantity available for the quantity recorded.
23 Fiscal Share Sub Total Sub Total values for each Fiscal Share.  Includes the name of the Share, SUM of all Stockpile Recorded this period, SUM of Period Payment this period, SUM of Stockpile to Date, and SUM of Payment to Date
24 Total Contract Amount Displays the Current Contact Amount value from Project Information
25 Percent Completed to Date Calculation of total Payment to Date/Total Contract Amount
26 Stockpile Recorded Total SUM of all Stockpile Recorded this period
27 Period Payment Total SUM of Period Payment this period
28 Stockpile to Date Total SUM of Stockpile to Date
29 Payment to Date Total SUM of Payment to Date
30 Retainage this Period Displays the Retainge entered for this period from the Pay Estimate Data Set
31 Retainage to Date Accrued value of all Retainage entered from previous pay periods and the current pay period
32 Total Stockpile and Payment to Date minus Retainage Calculation of Total Stockpile + Payment to Date - Retainage to Date (note: this calculation may be different for different Progress Payment Reports.  Please read the label of the totals value to know if Retainage is withheld or not)
33 Pay Estimate Remarks Displays the Pay Estimate Remarks entered for this period from the Pay Estimate Data Set
34 Page Number Displays page n of n
35 Date Generated Displays the date the report was run in FACS

 

Once your Progress Payment Report has been displayed, it can be downloaded in the following formats:

  • PDF
  • CSV
  • Excel

FACS_Report images for Support Site_Print Report Options

# Description
1 Select Format for download
2 Select Paginated or not (Paginated is recommended for PDF, but not recommended for csv or Excel)
3 Click to download the compiled report in the selected format

 

To learn more about reports, please see the related support pages on How to Run a Report and How to Export a Report.

 

If you have any questions, or need additional assistance, please reach out to our support team at support@facsware.com and we will be happy to assist you.